Chronology of EIA for the proposals for Glenelg redevelopment |
|
1984 - 1987
|
The Jubilee Point proposal
The first attempt at the redevelopment of the Glenelg Foreshore. Failed due to local opposition and to fears of a blow-out in sand management costs. | |
|
1990 - 1993
|
The Four Proposals for Glenelg Foreshore development
The second attempt at redevelopment: the four competing proposals. Failed due to developer being unable to raise capital (collapse of State Bank). | |
| 1993 | Development Act 1993, election of Liberal Government | |
|
January 1994
|
Release of Planning Strategy for Metropolitan Adelaide
| |
|
2 October 1994
|
Government announces $4m to clean up Patawalonga
- Government seeks expressions of interest for Glenelg redevelopment - infrastructure works to remedy environmental problems separated from commercial development, to be undertaken by State Government - availability of Commonwealth funding under Building Better Cities program - discussion paper is released - first mention of proposal for boat harbour at West Beach estimated construction cost - $5 million estimated sand management cost - $500,000 per year | |
|
February 1995
|
Holdfast Shores Consortium is selected to prepare Master Plan
- partners - Baulderstone Hornibrook, Kinsmen and Woodhead Firth Lee - Connell Wagner and Rust PPK as consultants - new development based on earlier Holdfast Quays proposal - earlier EIS prepared under superseded 1982 Planning Act deemed still relevant - Amendments prepared under Section 47 of Development Act 1993 | |
|
25 July 1995
|
Decision by Minister for Amendment to the EIS under Section 47
- on the Development Proposal for the Glenelg Foreshore and Environs - infrastructure proponent now Urban Projects Authority | |
|
May 1996
|
First Amendment to the EIS (AEIS) is released
- prepared by the Minister for Housing and Urban Development - on behalf of the proponent, evaluating the amended Holdfast Quays proposal - public exhibition 13 May - 24 June 1996 - 181 submissions | |
|
31 August 1996
|
The first Amendment to Assessment Report is released
- conditional development approval granted for infrastructure works at the Patawalonga mouth | |
|
April 1997
|
The second Amendment to Assessment Report is released
- West Beach Boat Harbour | |
|
12 May 1997
|
Ministerial PAR (Plan Amendment Report)
- to change zoning to allow construction of West Beach Boat Harbour - very few details, limited opportunity for public comment | |
|
July 1997
|
The second AEIS is prepared by the proponent (MFP Projects Board)
- addressing further works at the Patawalonga mouth | |
|
September 1997
|
The third Amendment to the Assessment Report is released
- assessing the works detailed in the second AEIS | |
|
16 March 1998
|
Construction of West Beach Boat Harbour begins
- protesters attempt to blockade site | |
|
March 1999
|
Completion of West Beach Boat Harbour
- actual construction cost - almost $17 million - estimated sand management cost (Holdfast Shores/West Beach) - $1.7m per year Source: "Carting sand $8m dredge on the taxpayer" The Advertiser, 20/2/2003 | |
|
July 1999
|
The third AEIS is prepared by the proponent (Minister for Govt. Enterprises)
- evaluating the Barcoo Outlet Stormwater Diversion Option | |
|
August 1999
|
Issues Paper for The Holdfast Shores - Stage 2 proposal is released
- consultation to 10/9/99 | |
|
October 1999
|
Guidelines for The Holdfast Shores - Stage 2 proposal are released
| |
|
December 1999
|
Conditional Development Approval is granted for the Barcoo Outlet
| |
|
December 1999
|
A Development Report is prepared by the Holdfast Shores Consortium
- addressing Stage 2 of the Holdfast Shores proposal | |
|
January 2000
|
The fourth Amendment to Assessment Report (Barcoo Outlet) is released
| |
|
January 2000
|
The Assessment Report for the Development Report is released
- considering only part A of Stage 2 | |
|
June 2000
|
Conditional development approval is granted for Stage 2A
| |
|
July 2000
|
The DAC grants development approval to construct the Barcoo Outlet
| |
|
December 2000
|
The Stage 2A proposal is amended
- again granted conditional development approval | |
|
September 2001
|
Amendment to the Development Report for the Stage 2A proposal
- released for public comment |